Prior Notification Proposed Demolition Checklist

Prior Notification Proposed Demolition Checklist

This checklist refers to applications for prior notification in respect of proposed demolition.

You can read National Guidance Notes relating to this Checklist here.

National Requirements

All submitted plans must incorporate a drawing number and title.

Links to Required Documents

Document Requirement

Application Form

Required in all cases

Location Plan

Required in all cases

Fee – Prior Approval

Required in all cases

Demolition Method Statement (see below for detail)

Required in all cases

Display of Site Notice

Required in all cases

Local Requirements

Links to Required Local Documents

Document Requirement

Site Plan

Required in most cases

Demolition Method Statement

A demolition and construction management plan should include:

  • a noise management plan including a scheme for the monitoring of demolition noise
  • a scheme for the control of dust arising from demolition works
  • a scheme of chassis and wheel cleaning for demolition vehicles including contingency measures should these facilities become inoperative and a scheme for the cleaning of affected public highways
  • a scheme of working hours for demolition works
  • a scheme for demolition access from the highway including measures to ensure that all demolition vehicles can enter the site immediately upon arrival, adequate space within the site to enable vehicles to load and unload clear of the public highway and details of any haul routes across the site
  • a scheme for parking of contractors vehicles
  • a scheme for access and deliveries including hours.